![]() |
|
| Check
this
web
page
for
the
latest
news
and
photos
of
the
new
Salesian
High
School
Gym. |
|
| Work Inside the Gym Work has moved to the inside of the new gym. There are not many changes to the nearly completed facade. (July 22, 2010) Click on any picture below for a larger view. |
|
| The
pictures above show the entrance to the new gym and the hallway through
the front door. |
|
| The
pictures above show the inside of the gym area facing west (at left)
and east. |
|
| The pictures above show the wrestling room (at left) and one of the shower/locker rooms (at right). | |
| Latest Pictures:
Inside the Gym Click here to see pictures of work inside the gym. |
|
| Racing to the Finish
Line Work
continues
at
a very fast clip. In the picture below, work on the
facade is almost completed. With the "old gym" shown at the far
right, it's easy to see how the new gym was designed to resemble the
"arts-and-crafts" architecture of the old. gym Although it can't
be seen in this picture, work inside the gym is also moving
quickly. The wrestling and conditioning rooms, and the gym
offices and locker rooms are all framed. Sheet rock covers the
walls in the gym area and is going up on most other areas. (July 6, 2010)
![]() |
|
| New Blacktop During
the
night,
workers
put down a new layer of blacktop, resurfacing the two
school parking lots and connecting roads. It gave the new gym a
finished look as the areas around the gym clean up. (June 25, 2010)
![]() |
|
| Work on the Facade
Moves Quickly Workers
continued
to
complete
the
new gym's facade. A course of stones
begin to fill the bottom half of the gym facade. Exterior work
continues on the east, west, and north sides of the gym, and curbs were
poured. The entire back parking lot will receive a new layer of
blacktop up to this new curb in front of the gym. (June 22, 2010)
![]() |
|
| The Facade Takes Shape Work
on
the
gym
facade
is
is moving very quickly. The poured cement
entry stairway and ramp are shown below the entry porch. The west
side of the building (far left) is in the process of being closed
up. A gigantic crane loaded the air-conditioning units over the
roof and through the only large opening left, on the gym's east side at
the end of the retaining wall (far right). (June 18, 2010)
![]() |
|
| Take a Peek Inside Click here for pictures of the construction INSIDE the new gym. |
|
| Details Emerge The
picture
below
shows
details
added
to
the
gym
exterior.
Styrofoam
forms
above the
window spaces recreate the "Arts-and-Crafts" architectural elements of
the old
gymnasium. After several layers of stucco were applied to the
Styrofoam, workers began to paint the areas of the exterior walls that
are finished (the beige area at the center - refer to the artist's rendering at the bottom of the page). Workers
can also be seen building the form for the concrete steps up to the
main gym door. At the far right, the completed retaining wall can
also be seen behind the Japanese Maple tree. (June 11, 2010)
![]() |
|
| The Pace Picks Up In
the
picture
below,
workers
can
be
seen
applying
Styrofoam
panels
to
the
upper
walls of the gym building. Also shown (the gray area
in the center) is the first layer of stucco applied over the Styrofoam
panels. You can also see the opening on the north side of the gym
(far left in the photo) that allows big machinery to enter. (June 8, 2010)
![]() |
|
| Change of Plans With
the
Tyvek
removed
from
the
top
of
the
gym
building,
workers
applied
a
sealant
coat (the pinkish color) and then began applying a layer of
Styrofoam panels. (June
5,
2010)
![]() |
|
| All Wrapped Up As
spring
turned
into
the
hot
and
sticky
month
of
June,
workers
began
wrapping
the
gym
building
in protective Tyvek and adding the porch-like
entry way. It cannot be seen, but the gym floor was also poured
and workers have begun building interior walls. (June 2, 2010)
![]() |
|
| A Building Emerges As
the
gloomy
spring
continued,
workmen
completed
installing
the
insulation
panels.
For
the
first
time,
the
new
gym
appears as a
solid structure on our campus. Many students first notice that
the gym is almost the size of the entire school building. At the
right of the picture can also be seen the machinery used to pour the
cement retaining wall on the east side of the gym. (May 25, 2010)
![]() |
|
| Walls Begin To Go Up On
a
rainy
day,
May
18,
2010,
workmen
began
applying
base
insulation
panels
to
the
aluminum
studs.
(May
19,
2010)
![]() |
|
| Walls and Windows
Appear By
mid
May,
workmen
added
aluminum
studs
to
the
upper
walls
of
the
new
gym.
It's
becoming
easier
and
easier
to
visualize the new
structure on our campus. (May
14,
2010)
![]() |
|
| A Ring of Steel By
early
May,
workmen
install
and
weld
together
steel
embedded
into
the
top
of
the
cinder
block
walls
to
reinforce
them.
Note
also
at the right metal
studs installed, creating the far right wall of the gym. The form
for the front entrance steps and ramp have also been poured and can be
seen at
the door opening at the right. (May 6, 2010)
![]() |
|
| Walls Surround the Gym Workmen
continued
a
course
of
cinder
block
around
the
bottom
half
of
the
new
gym.
The
cinder
block
will
back
the
stucco
which
will
make up the
bottom half of the exterior walls (see the architect's rendering
below). Note also that workers inserted insulation beneath the
roof rafters. (April
24,
2010)
![]() |
|
| The Walls Begin to
Rise Right after the roof was completed, workmen began laying cinder blocks and the new gym walls began to appear. (April 20, 2010) ![]() |
|
| Raising the Roof! By
mid-April
the
gym
roof
was
completed.
During
the
Easter
break,
electricity
was
brought
to
the
gym
structure.
(Note
the
green
electrical
box
in
the
lower
left.)
Water pipes began to appear
and, when this picture was taken, workers were hanging the pipes for
the sprinkler system from the underside of the roof. (April 17, 2010)
![]() |
|
| The Frame Fills In During
the
month
of
March,
workers
continued
adding
steel
to
the
gym
frame.
By
mid-March
the
roof
begins
to
materialize.
With
workers
up
and
all
over
the
roof,
the gym work area begins to resemble
a circus with trapeze artists. (March 19, 2010)
![]() |
|
| The Steel Frame Is
Completed By
the
beginning
of
March,
workers
completed
assembling
the
frame
of
the
new
gym.
It
is
now
easy
to
visualize
the
new
gym
and
the
space
it
will
take
up on our campus. Workers continue to add support beams
to the frame, but the parking lot area that was full of steel beams is
not almost completely empty. (March 4, 2010)
![]() |
|
| The Beams Go Up During the February Break, workers used cranes to begin the assembly of the gym's steel girders. (February 19, 2010) ![]() |
|
| The Steel Arrives On
Friday,
February
12,
after
the
biggest
snow
storm
of
the
season,
cranes
and
flat-bed
trucks
loaded
with
steel
beams
take
over
the
Salesian
High
parking
lot.
Assembly of the
gym's outer walls is next! (February 12, 2010)
![]() |
|
![]() |
|
"Build Your House on
Rock" Our
new
gym
for
the
most
part
is
set
on
rock;
you
can
see
the
footing
of
concrete
and
reinforcing
bars
in
the
pictures
above
and
to
the
left.
The
foundation
differs
in
places
because of the soil and rock underneath or the load
it will have to carry when the gym is done. An example would be
the "stepped footings" found in the lower left of the pictures.
Our gym will have a slab foundation. In the picture at the left,
you can
see workers prepare footers that span the building and which will
support the floor and
stiffen the structure. The high wall in the back is needed for
the air-conditioning units that will be put on the roof. (February 4-5, 2010)
Technical
information
courtesy
of
Fr.
Jim
Mulloy,
SDB
|
|
The Foundation Nears
Completion![]()
During
the
month
of
January,
work
on
the
foundation
continued.
A
platform
was
created
upon
which
the
new
gym
will
sit.
In
the
picture
above,
retaining
walls
around
the
back
of
the
gym
are being
poured. The platform is filled with packed dirt and workers are
currently digging trenches for pipes. (January 26, 2010)
|
|
Work Continues
through the Cold Winter![]()
On
December
17,
2009,
Despite the coldest winter weather in years and an occasional dusting of snow, work continues at a fast clip on the new gym. as shown above at the right. By early January of 2010, the footings of the gym's foundation are nearly completed. (January 8, 2010) |
|
| Work Begins Again! After
a
bit
of
a
delay,
work
resumed
on
the
new
school
gym
in
December.
The
new
contractor
set
up
a
trailer
at
the
work
site,
and portable bathrooms - a sure sign that work was to begin again, and
workers resumed work on the foundation. In the
pictures below, gravel and rebar are put into place, and the forms are
built in preparation
for the pouring of the foundation. In one day this past week,
workers cut a trench completely across the property, laid pipe, and
covered up the trench by quitting time. (December 16, 2009)
|
|
![]() |
![]() |
![]() |
|
| New Gym Foundation
Ready! By the middle of September, the trench for the foundation was dug out and pounded away from the rock. (September 17, 2009) ![]() |
|
| Make Way for the
Foundation! By Friday, August 7th, the space for the new gym's foundation is nearly all cleared away. (August 7, 2009) ![]() |
|
| The Big Machines
Clear the Land! By Friday, July 24th, a gap for the new gym's foundation was cut into the rocks and hillside. (July 24, 2009) |
|
| Pounding Away the
Rocks! Monday, July 20th, the big machines attack the rocks to level a space for the new gym's foundation. (July 20, 2009) |
|
| The Digging Begins! Wednesday, July 15th, the hillside by the old basketball court begins to disappear! (July 15, 2009) ![]() |
|
|
The Big Trucks
Arrive! The Trees Go!
Early
Tuesday
morning,
July
14,
2009,
large
trucks
arrived
on
Main
Street.
The
equipment
entered
the
school
property
through
an
opening
cut
into
the
white
metal
fence.
All
day
trees
were
cut
down,
logs
loaded
onto
flat
bed
trucks,
and
branches
fed into a chipper. The spot
for the gym is now cleared of trees.
|
|
|
At left, giant trucks line up on Main Street in front of the school. At right, the equipment is off loaded and moves into position to clear the trees off the site. Below left, the new gym site with trees cut and removed. Below right, trunks of the trees loaded for removal while the chipper demolishes branches and leaves. |
|
| Clearing the Area! On a rainy Thursday morning, June 11, 2009, the jackhammers and the backhoe arrived to take down the basketball backstops and to begin the digging for the new gym! |
|
![]() Francesco & Luis
begin to remove the backstops.
|
![]() A
backhoe digs out the basketball posts.
|
![]() The work site begins to look busy! |
|
| New Gym Plan Approved!
At
their
meeting
on
May
26,
2009,
the
City
of
New
Rochelle
Planning
Board
unanimously
approved
Salesian
High
School's
plan
for
the
new
gym.
Members
of
the
Premium
Point
Park
Homeowners
Association
present
at
the
meeting
were
impressed
with
Salesian
High's eagerness to
be a good neighbor and adhere to their requests.
![]() Workers begin to appear at the site of the new gym. |
|
| Salesian High School
Breaks Ground on the Br. Jim Wiegand, SDB Athletic Center Legendary Salesian Basketball Coach Memorialized
“After
months
of
planning,
our
long
awaited
dream
to
construct
a
new
athletic
facility
at
Salesian
High
School
will
finally
become
a
reality,”
announced
Fr. Patrick
Angelucci, SDB, the school’s Director/President.
The students, alumni, faculty, administration and representatives of the Salesians of St. John Bosco held a groundbreaking ceremony for the Br. Jim Wiegand, SDB Athletic Center at the site of the new facility on Friday, May 1, 2009 at 9:15 A.M. “The new facility will provide much needed space to help meet the spiraling demands of the school’s growing athletic and performing arts programs,” said the school’s Principal John Flaherty. According to Mr. Flaherty, the facility will not only be a tremendous boost to the sports program; but, it will also help free up some much needed space in the existing gymnasium to house a band room and expand the drama program. It is well known that in his 18-year career at Salesian High School (1962-1980), Br. Jim’s athletic program provided a well-rounded, balanced, athletic program that raised school spirit and instilled principles of sportsmanship, competition, and fair play. His “Eagles” basketball team won a New York State Championship in 1976 as well as an unprecedented eight league championships - 1964, 1965, 1966, 1971, 1972, 1975, 1976, and 1979. Salesian High School alumni, especially Br. Jim’s former players, have expressed their enthusiastic support and are grateful that Br. Jim’s service to the school, its students and the Athletic Program will be memorialized in such a tangible and meaningful way. The Br. Jim Wiegand, SDB Athletic Center is the first free standing building erected on the Salesian High School Campus since the current gymnasium was built in 1927. Construction is expected to begin in late spring and completion is slated for December 2009. |
|
![]() |
![]() |
| Shown, above left, at
the groundbreaking are the Very Rev. James Heuser, SDB, Salesian
Provincial, Br. Jim Wiegand, SDB, Mr. John Flaherty, Principal, and Fr.
Patrick Angelucci, SDB, Director/President. Above right, Fr.
Heuser blesses the ground for the new gym assisted by Gregory Rivera
'09. |
|
![]() |
![]() |
| Above left,
representatives of the different Salesian High sports teams cheer Br.
Jim on as he empties the first shovel full. Above right, alumni
members of Br. Jim's winning basketball teams help to break
ground. Shown below, a group photo of the Salesian High students
and alumni assisting with the groundbreaking ceremony. |
|
![]() |
|
| |
|
|
At
the
Thanksgiving
school
Mass
this
past
November,
Salesian
High
Director/President
Fr.
Pat
Angelucci,
surprised
everyone
by
announcing
that
a
NEW GYM
will be built for Salesian High students. It will be located at
the site of the outdoor basketball courts, between the school building
and what will soon be called the "old gym." The fifteen thousand
square foot building, named after the Salesian’s legendary Basketball
Coach and Athletic Hall of Fame inductee Br. James Wiegand, SDB, is designed
by The General Steel Corporation and will house a regulation size
basketball court, bleacher seating for the entire student body, a
wrestling room, a strength and conditioning center, locker/shower
facilities and office space. The architect's renderings of the
new gym are shown below. |
|
![]() |
![]() |